Operator Reduced Non-Productive Time and Total Well Costs Using FLC 2000® in Mexico

Mexico
Challenge

An offshore operator drilling exploratory wells experienced high torque, lost circulation and hole collapse during drilling operations for the XUX-1 well. Cement plugs were placed across the thief zone but the operator lost circulation and ultimately increased drilling days and total well costs. The operator began drilling operations for a new well, KAA-1 and wanted to reduce costs compared to the XUX-1 well.

Solution

Working with Impact Fluid Solutions, the operator added FLC 2000 wellbore stabilizer to the drilling program for KAA-1. FLC 2000 was added to the 14 ½-in. and 17 ½-in. intervals to prevent lost circulation and reduce total well costs.

Results

During the 26-day drilling stage on the original XUX-1 well, 12 days were used fighting lost circulation and placing cement plugs. On the KAA-1, where FLC 2000 was added, mud losses were reduced and the operator decreased NPT and total well costs by completing the section in 10 days, a reduction of over 60% compared to the first well.

This website uses cookies to help us understand how our site is used and improve the user experience. By using our site, you consent to the use of cookies. To learn more or manage your cookie preferences, please see our privacy policy.